February 2009 - June 2009
- OUED to appoint main contractor for the overall project
- Agree UPS and fire suppression provision with cost estimates
- Agree the size of the data centre hall
(Agreed a layout of four aisles with 62 cabinets - around
15 cabinets per aisle - with cold air containment) - Calculate the indicative budget for the 'soft fit-out' - internal
networking, power distribution, cabinets, monitoring sensors,
and shared server infrastructure
- Submit
paper to PRAC Budget Sub-committee [PDF 55 KB] seeking approval for allocating 'soft fit-out'
budget within overall data centre budget
-
June 2009 report - Central Machine Room [PDF 74 KB]
July 2009 - November 2009
- Finalise space allocated in the Oxford Molecular Pathology
Institute (OMPI) with the University Estates Directorate
- Building contractors to demolish Leslie Martin site and begin new building
- Agree power distribution with building contractors
- Agree cooling specification: air conditioning and chilled water feed
- Basement concrete due to be poured by the last week of November 2009
- Expected confirmation of VAT status from Her Majesty's Revenue and Customs
- Agree raised floor specification and feeding of power and data
-
November 2009 report - Central Machine Room [PDF 100 KB]