- Data Centre Operations Team begin hardware evaluation programme - consult with appropriate groups within OUCS
- May 2010 building topping out expected
- May 2010 report - Central Machine Room [PDF 104 KB]
- Present at ITSS Conference, June 2010, giving details and benefits of Shared Data Centre
- Liaise with building contractors (Maceplus) on cabinet positioning and high level containment to ensure correct positioning of high level containment prior to the soft fit
- Establish working group within OUCS (Shared Data Centre working group) to oversee fit-out and on-going running of the centre
- Establish Technical Services Team to advise on the kit for the soft-fit (cabinets, power bars, structured cabling etc)
- Expect UPS systems to arrive on site
- First inspection of site - check fire detection and fire suppression systems are in place
- Work on soft-fit tender (which will then be put out to tender over the next 8-12 weeks)
- Expect delivery of security system
- November 2010 report - Central Machine Room [PDF 108 KB]
- Expect Data Centre space to be handed over to OUCS in December 2010
- In consultation with TST team and Shared Data Centre Working Group produce costings for the use of rack-space - include electricity use and cooling charges
- Submit the soft-fit tender (ITT) documentation to purchasing
- Advertise closed tender - OUCS to invite qualified companies with Systimax installation accreditation to bid for the process
- Survey of ITSS (including central IT providers) to establish day one colocation demand
- Finalise communications - web site etc for services
- Develop policies and procedures for services
- Carry out load testing in early January 2011 prior to the main contractors leaving site (test power distribution and air handling and cooling within the centre)
- If tests successful - Data Centre to be signed off and OUCS to formally take ownership
- Feb - April 2011, data centre fit-out and testing
- Finalise service arrangements and allocation of space within the Date Centre
- August 2011 Data Centre opens for business