Report on OUCS 5-year Vision 2005-2010
In keeping with University policy, OUCS produced a 5-year vision in 04/05, complete with short-term, medium-term, and long term objectives. At the end of that report (circulated to ICTC) a list of objectives and activities was provided. This brief summary acts as a progress report on these activities, and a signing-off of certain goals which have been achieved during the year.
A quick summary of the goals outlined in Section 1 below is as follows(Section 2 below presents the original breakdown of objectives and goals.):
- 88 specific goals were identified in the original plan
- OUCS has completed 28 of these
- 26 further goals are in progress, and some of them are near to completion
- Of the remaining goals 29 have been identified as continuing activity for OUCS, i.e. part of our core continuing remit
- Only 3 goals have been identified as being directly affected and
delayed by the emerging Enhanced Computing Environment
* Only two goals have been noted as abandoned — one due to it being taken up by the University’s Web Strategies Group, and the other relating to the portal project (see below).
We suggest that this demonstrates a very productive year for the department in that we have achieved most of the goals (or are working on them) identified by OUCS and ratified by ICTC. However, we would like to draw attention to a few important points:
- This success has been achieved in spite of the constraints currently imposed on OUCS in terms of resourcing, and many crucial developments have not been allowed to go ahead due to lack of resources.
- We feel it is important to stress that any new service asked of OUCS has a considerable resourcing implication in terms of capital costs, pressure on existing facilities (notably our machine room which currently is filled to capacity), and staff costs (development, testing, maintenance, and support). The marginal costs of such services needs to be recognised centrally, and as OUCS is currently operating at capacity any new service can only be accommodated if it is matched by new funding or an existing service is ceased.
- Three key projects and initiatives did not succeed due to the fact that the University did not allot strategic funding to these initiatives. These were:
a) A University-wide filestore
b) A roll-out of wireless across University departments and public places
c) The development of the University portal
In Hilary Term we will revise our report and produce a new 5-year vision statement (covering 2006-2011). This will be done in the light of forthcoming University guidelines on producing such reports within the general framework of the Corporate Plan, and the emerging University-wide ICT Strategy.
Section 1: Summary of Goals Tasks
| Goals/Tasks | Relates to Objective | Comments |
| Completed | ||
| Complete the final parts of the backbone network upgrade to 10 Gbps, with minimal disruption to service | 4.1.1, 4.1.4 | |
| Seek University support and funding for hardware required | 4.1.1, 4.1.3 | |
| Transfer telecommunications services and NSMS web service to new technology | 3.5 | |
| Complete OUCS wireless pilot project | 4.1.3.2 | Information available at http://www.oucs.ox.ac.uk/network/wireless/ |
| Participate in University decision-making regarding extent and funding of future developments | 4.1.3.2 | Funding refused |
| Introduce additional TSM servers to cope with continued growth in demand | 4.2 | |
| Evaluate and introduce new TSM features (such as collocated files on tape) to improve quality of service | 4.2 | Is also a continuing activity. |
| Conduct pilot study/studies for the Central Filestore leading to a firm proposal | 4.2 | Funding refused |
| Update the hardware base underlying central service provision as required, taking advantage of developments in data storage technology (and potentially integrating with the Central Filestore) | 4.2 | Hardware updated but funding refused — see above |
| If appropriate, migrate and enhance registration database services to new server | 4.5.1 | |
| Investigate the integration of the existing OUCS Kerberos implementation with Novell’s NMAS method to provide integrated authentication across the department for all types of PC workstations | 4.5.1 | |
| Produce annual report on activities, common problems etc, primarily for ITSS conference | 3.4 | |
| Identify and document suite of general purpose technical support procedures (e.g. operating system re-install | e.g.www.oucs.ox.ac.uk/helpcentre/troubleshooting/winxp | |
| Re-launch internal home page as a collaboratively authored WIKI | 3.4 | |
| Master source of all static OUCS web pages held in validated XML | 5.1 | |
| Develop and deploy mechanism for routine monitoring and 6-monthly reporting on compliance of all OUCS web services with W3C WAI AA standards | ||
| Implemented recommended search engine solution and promote to ITSS and institutional webmaster | 5.1 | |
| Implement pilot WIKI application (for Help Centre staff) and report on usability and appropriateness of this technology | 5.1 | |
| Provide input to email addressing policy review | 4.1.4 | |
| Provide facilities for users to manage their own email routings | ||
| Deliver draft Infrastructure Metric to ICTC and seek agreement that trial can be made | 4.4.1 | |
| Assist ICTC in implementation of trial Infrastructure Metric and then full evaluation | 3.1, 3.2, 3.3 | |
| Mount initial OUCS course material online under the VLE, and report to SMG and ICTC | 4.3 | Available at http://www.weblearn.ox.ac.uk/bodington/site/asuc/oucs/itlp/ |
| Aim to implement modular course booking, and report to SMG | 4.3 | |
| Investigate and promote the next level of VLE development and report to SMG | 4.3.1 | |
| Outline a (Service-Oriented) architecture for a VRE, which comprise interoperable services in support of the research life-cycle; report to ICTC | 4.4.1 | This is taking place via the three VRE projects |
| Develop points of integration between Weblearn, Webmail and the OUCS portal | 4.4.1 | |
| Complete new secure office | 5.4 | |